PSC gives final OK for wind farm

By Christian M. Giggenbach
Register-Herald Reporter

Just two days after Gov. Joe Manchin introduced a sweeping renewable energy proposal to lawmakers, the state Public Service Commission on Friday gave its final stamp of approval on a $300 million Greenbrier County wind farm.

The much anticipated decision came nearly 41/2 years after Chicago-based Invenergy first applied for a siting certificate to construct 119 giant wind turbines on 23 miles of mountain ridges owned primarily by MeadWestvaco. From the start, Invenergy officials touted the nation’s need for clean, renewable energy and the hundreds of jobs that would be created from the construction of the Beech Ridge Energy wind farm located about 9 miles east of Rupert.

Manchin introduced the Alternative and Renewable Energy Portfolio Act to lawmakers Wednesday evening. It would eventually require 25 percent of electricity sold in West Virginia to be generated from wind, solar and hydro-electric facilities.

And, as if on cue, the Manchin-appointed, three-man PSC green-lighted the controversial Greenbrier County project by publishing its 41-page decision late Friday afternoon.

During its deliberation, the PSC sorted through more than 800 pages of supporting documents supplied by Beech Ridge that bolstered the energy company’s claim it had complied with 18 preconstruction conditions previously mandated by the PSC in 2006.

“ ... the commission concludes that all pre-construction conditions have been met and authorizes construction begin on the proposed Beech Ridge Energy LLC wholesale electric generating facility in Greenbrier and Nicholas counties,” Friday’s order stated.

Construction of the 186-megawatt wind farm, which will require a 138-kilovolt transmission power line that connects to an Allegheny Energy substation near Nettie, is anticipated to take about seven months and will create about 200 jobs and between 15 and 29 full-time, permanent jobs.

“While we have not had time to review the entire order, Beech Ridge Energy is very pleased that the Public Service Commission has given us the green light to start construction,” said Dave Groberg, director of business development for Invenergy. “Despite the current economic conditions, we are ready to put skilled West Virginians to work building this clean, renewable energy project this year.”

Groberg previously said construction of the wind farm, barring any appeals, could begin as early as this spring.

-----

Beech Ridge’s most vocal opponents, the grassroots organization called Mountain Communities for Responsible Energy, and Jeffrey and Alicia Eisenbeiss, fought the construction of the wind farm from its inception. A majority of the MCRE members, like the Eisenbeisses, owned property adjacent to proposed wind turbine sites.

MCRE officials could not be reached for comment late Friday.

MCRE had argued, among other things, the wind farm would decrease property values, spoil scenic views and could potentially kill endangered bats. The decommissioning, or tearing down, of the 400-foot-tall turbines after their useful life was over also became a core issue as the denials of MCRE appeals began to pile up.

In its decision, the PSC supported Beech Ridge’s schedule of additional financing through bonds or escrow accounts to ensure money would be available should the turbines be dismantled at the end of or during their 20-year life span.

The PSC decision order said, “Beech Ridge shall tender a letter of credit in favor of the Greenbrier County Commission” in the amount of $2,500 for each turbine for the first five years of the project. That cost rises incrementally to $20,000 per turbine after 16 years.

The order also provides that Beech Ridge shall pay the county $400,000 in property taxes each year.

“It is further ordered that Beech Ridge shall submit to the (PSC) for its review and approval an ‘as built’ decommissioning report when construction is completed and an updated decommissioning report every five years,” the order said. “The commission reserves the right to adjust the amount of security required if an increase is warranted by the results of the ‘as built’ review or any of the periodic updates.”

Although the PSC also ordered Beech Ridge’s case be removed from its docket, state laws allows for a 10-day window for an appeal. MCRE’s officials have previously said they would exhaust all appeals and has not discounted a possible appeal to the state Supreme Court.

The PSC’s Web site listed more than 723 separate filings since Beech Ridge’s application for a siting certificate in November 2005.

MCRE’s first bid to derail Beech Ridge’s wind farm in the state Supreme Court failed in a 4-1 decision.

— E-mail: cgiggenbach@register-herald.com

print this story  



autoconx

Premier Guide
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide

Find a job! Find a Home! Find a car!

Premium Jobs

JOB FAIR - NOVEMBER 20TH
Job FAIR. Massey Energy is accepting experienced underground applicants. Our expanding operations are located in Raleig...>MORE

UNDERGROUND COAL MINING FOREMAN / COORDINATOR
GMS Mine Repair and Maintenance is seeking a Virginia certified Underground Coal Mining Foreman / Coordinator for work i...>MORE

CASEWORKER
Caseworker. A part-time with possible full-time potential position managing the monthly income of mentally and physicall...>MORE

LICENSED PRACTICAL NURSE - MONTGOMERY GENERAL ELDERLY CARE
MONTGOMERY GENERAL ELDERLY CARE is accepting applications / resumes for Licensed Practical Nurses. Qualified candidates ...>MORE

ACCOUNTANT, CPA OR CPA CANDIDATE
CPA office looking for accountant, CPA or CPA candidate, southern WV, very busy practice. Ability to become an owner. Be...>MORE

EMT APPRENTICESHIP PROGRAM
EMT Apprenticeship Program. Jan-Care Ambulance Service is currently accepting applications for our Emergency Medical Tec...>MORE

LICENSED PRACTICAL NURSES
Make a difference in the life of a veteran. Are you interested in working in a state-of-the-art, one-of-a-kind organizat...>MORE

NURSE PRACTITIONER - GREENBRIER CO.
Nurse Practitioner for busy medical office in western Greenbrier County. Must be able to work evenings and weekends. Ful...>MORE

CERTIFIED NURSING ASSISTANT - MONTGOMERY GENERAL ELDERLY CARE
MONTGOMERY GENERAL ELDERLY CARE is accepting applications / resumes for Certified Nursing Assistants. Applicants may app...>MORE

TEREX / SHM HIGHWALL MINER OPERATORS, HIGHWALL MINER FOREMAN, CERTIFIED ELECTRICIANS
Pocahontas Coal Company’s North Star One Surface and High Wall Miner operations located near Beckley, WV is now acceptin...>MORE

See all ads

Premium Jobs

See all ads


 

Community Newspaper Holdings, Inc.CNHI Classified Advertising NetworkCNHI News Service
Associated Press content © 2009. All rights reserved. AP content may not be published, broadcast, rewritten or redistributed.
Our site is powered by Zope and our Internet Yellow Pages site is powered by PremierGuide.
Some parts of our site may require you to download the Flash Player Plugin.
View our Privacy Policy
Advertiser index